Here is this weeks update on the showers. Concrete was poured today to fill in around the new plumbing and where the stepdown showers were. Tomorrow they will start framing the walls and fir out the adobe brick with 5/8 metal so they will accept duro rock from the floor up 48 inches and sheet rock to the ceiling. ( The 2x4's you see in the picture are still the braces holding up the ceiling and roof where the interior abode walls were taken down.) Then more electrical and plumbing before the sheet rocking which is scheduled for 3 weeks from now. The adobe walls will be tiled up 48 inches and sheet rocked to the ceiling. The meeting between the Constructions Manager, his supervisor, myself, and Mr Hays was very informative with all of us learning something. I people and businesses should have to go through a class in how to read plans. HA!